Construction on Forsyth


Construction on Forsyth Avenue, in front of the hospital’s underground parking garage, will begin August 27 and run until August 30.

An elevated crosswalk will be built and a portion of the sidewalk on the north and south sides of the crosswalk will be replaced.

Monday August 27

The sidewalk curbs will be prepared on both the north and south side of Forsyth.

Tuesday August 28

The northern portion of the elevated crosswalk will be constructed.

Eastbound traffic in the south lane is available.

No westbound traffic access.

Wednesday August 29

The southern portion of the elevated crosswalk will be constructed.

Eastbound traffic in the north lane is available.

No westbound traffic access.

Thursday August 30

Closing date. Normal traffic may resume.

Forsyth Construction