Construction on Forsyth
Construction on Forsyth Avenue, in front of the hospital’s underground parking garage, will begin August 27 and run until August 30.
An elevated crosswalk will be built and a portion of the sidewalk on the north and south sides of the crosswalk will be replaced.
Monday August 27
The sidewalk curbs will be prepared on both the north and south side of Forsyth.
Tuesday August 28
The northern portion of the elevated crosswalk will be constructed.
Eastbound traffic in the south lane is available.
No westbound traffic access.
Wednesday August 29
The southern portion of the elevated crosswalk will be constructed.
Eastbound traffic in the north lane is available.
No westbound traffic access.
Thursday August 30
Closing date. Normal traffic may resume.